Investments

Finished

Creation of a pilot line with the aim of validating the semi-technical scale of the technology for producing highly specialized, flame-retardant hydraulic liquids and innovative additives, enhancing the performance characteristics of plastics and lubricants

Schedule 20017 - 2021 Benefits Production of a new range of specialist products Expanding the assortment of marketed products Development of new technological solutions Application…

More
Finished

Construction of HCl absorption station, Isopropylphenol purification plant together with construction of storage base and Roplast distillation plant

Schedule 2010 - 2012 Benefits Increasing installation efficiency Environmental protection New product range Increase in production capacity of Phosphorus Aryl compounds

More
Finished

Construction of sewage treatment plants

Schedule 2009 - 2012 - construction of chlorophenol-containing wastewater treatment plants Benefits Reduction of hard-to-dissolve organic compounds, reduction of COD Chlorophenol reduction, AOX reduction, reduction…

More
Finished

Construction of a modern ethoxylate factory in Płock

Schedule 2011 - commissioned Benefits Increase in production capacity by 30 000 tonnes/year Direct location of the plant at the ethylene oxide supplier

More
Finished

Construction of a new HCl Synthesis Plant together with the expansion of the warehouse base

Schedule 2011 - commissioned Benefits Increase in production capacity by 20 000 tonnes/year Increase in hydrochloric acid storage capacity Improvement of the chlorine balance

More
Finished

Construction of diaphragm electrolysis plant – Stage I and extension of NaOH and NaOCl formulation and loading stations

Schedule 2010 - commissioned Benefits Reduction of production costs (electricity) Moving to more environmentally friendly technology Expanding the product range Increasing the efficiency of loading…

More
Finished

Construction of a production for polyols iPol

Schedule 2009 - commissioned Benefits Production of highly specialised polyols Extension of the range of products sold

More
Finished

Construction of sulphate plants with a capacity of 30 000 t/year

Schedule 2008 - commissioned Benefits Increase in sulphate production capacity from 10 000 to 40 000 tonnes/year

More
Finished

Construction of a heat and power plant

Schedule 2008 - commissioned Benefits Reduction of harmful emissions Increasing security of heat and electricity supply EU grant PLN 19.5 million

More
Finished

Expansion and intensification of PCI3 and POCI3 production

Schedule 2008 - commissioned Benefits Increased safety based on HAZOP analysis Increase of PCI3 production capacity from 3 600 to 7 000 tonnes/year

More
Finished

Modernization of the chill-water pumping station

Schedule 2008 - commissioned Benefits Reduction of electricity consumption 0 92% at pumping station I and 42% at pumping station II Noise reduction of approx.…

More
Finished

Flame retardants – extension of the plant up to 8 000 tonnes

Schedule 2008 - commissioned Benefits Increase the production capacity of flame retardants to 125%. Expansion of infrastructure (absorption stations, storage tanks) Reduction of environmental impact…

More
Finished

Construction of a new polyol installation

Schedule 2006 - commissioned Benefits Increase in production capacity from 33 000 to 60 000 t/year

More
Finished

Expansion of the propylene oxide and ethylene oxide storage base

Schedule 2006 - commissioned Benefits Increase of TP's storage capacity by 500 tons and TE by 430 tons Possibility of direct transmission of TE between…

More
Finished

Expansion of the storage base for raw materials for the production of flame retardants

Schedule 2006 - commissioned Benefits Increase in phosphorus storage capacity by 150 tonnes Increase in storage capacity of phosphorus trichloride and phosphorus oxychloride by 250…

More
Finished

Modernisation and capacity increase of the flame retardant plant

Schedule 2004 - commissioned Benefits 60% increase in flame retardant capacity Expansion of infrastructure (absorption station, storage tanks)

More
Finished

Expansion of the ethoxylate storage base

Schedule 2004 - commissioned Benefits Increase in storage capacity of ethoxylates by 2200 m3 Reduction of wastewater emissions by 5%

More
Finished

Modernization of pumping stations of the first and second degree of cooling water

Schedule 2004 - 1st stage pumping station put into operation 2005 - 2nd stage pumping station put into operation Benefits Reduction of electricity consumption by 92% at…

More
Finished

Replacement of the cold store at the propylene oxide plant and rocopoly from ammonia to freon

Schedule 2004 - commissioned Benefits Reduction of environmental nuisance (elimination of ammonia emissions) Reduction in operating costs by 35%

More
Finished

Membrane electrolysis

The main effect of the project is to reduce production costs by reducing electricity consumption. The implementation of the project will result in a fundamental…

More
Finished

Adaptation of environmental protection installations for scaffolding boilers to the new requirements of the IED Directive

Reduction of emissions from the installations of PCC Rokita SA CHP Plant to meet the stricter emission standards in force from 2016. The investment concerns…

More

PCC Rokita SA implements projects which are co-financed from public funds, including European funds

more